Capital Improvement Projects

Wastewater Treatment Plant

Triton Construction of Saint Albans was awarded a $196 million contract through a public bidding process in 2025 for the wastewater treatment plant expansion project. The project began in Spring 2026 and is expected to be completed in 2032.

This project has been several years in the making, and there will be numerous benefits to upgrading and expanding capacity of our plant. It will improve safety conditions for employees; support economic development growth in Huntington and the surrounding region; allow the Sanitary Board to meet state and federal environmental guidelines; and make the wastewater treatment process more efficient, ultimately saving rate payers hundreds of thousands of dollars annually.

The wastewater treatment plant was constructed in 1964, and a secondary treatment process was integrated into the plant in 1986. There have been few upgrades since then.

The plant serves approximately 27,000 metered customers in Huntington and surrounding areas, including customers served by the towns of Ceredo and Kenova and the Northern Wayne, Spring Valley and Pea Ridge Public Service Districts.

More than 325 miles of sewer lines, 47 sewage pump stations and 132 grinder pump stations help send sewage to the treatment plant, which has an average flow of 9 to 12 million gallons on a dry-weather day. It is the largest collection and treatment system in West Virginia.

The treatment plant, however, currently is at 98 percent capacity. On a wet-weather day, the treatment plant can process about 14 to 15 million gallons per day. Anything above that level is not treated to permittable limits and is discharged into the Ohio River, putting the Sanitary Board at risk of being fined by state and federal regulatory agencies.

The expansion project will enable the plant to treat 17 million gallons on a dry day and up to 64 million gallons on a wet-weather day.

The project, however, goes far beyond increasing capacity and ensuring wastewater is processed appropriately before it is discharged into the Ohio River. It also represents an investment in Huntington’s economic future.

An economic impact study conducted in 2024 by Chmura Economics & Analytics projected a total economic impact of $101.6 million, the creation and support of 618 jobs and $5.1 million in taxes paid to the city and state during the construction phase. After the expansion project is completed, it will contribute $293 million annually to the regional economy, supporting 1,292 jobs and generating $900,000 in tax revenue for Huntington every year.

3rd Avenue & 5th Avenue Separation Project

This project will mitigate frequent flooding at two intersections - 3rd Avenue and 24th Street and 5th Avenue and 25th Street. This will be accomplished by separating portions of the storm sewers from the combined sanitary sewer and installing pump station/force main systems to convey runoff from these two low-lying areas to the Ohio River. It will remove the stormwater of approximately 40 acres of drainage area from the Sanitary Board sewer system and treatment plant.

This project is critical because it will allow emergency-response vehicles to travel through town in the quickest manner during heavy rain. It also is important for efforts to redevelop the former ACF industrial site so that it can create jobs and strengthen the local economy.

The project began in June 2025 and is expected to be completed sometime in 2027.

4th Street & 13th Street West Pump Stations

The 4th Street and 13th Street West pump stations were designed and constructed in the 1950s but have seen few upgrades since then. Both stations also have experienced pipe failures and fires in the past. Additionally, while these stations were constructed with four pumps each, each station now has two or fewer pumps operating.

As a result of their limited capacity, our collection system is inefficient. Approximately 80 percent of the sewage collected in Huntington is pumped through the 4th Street and 13th Street West stations.

However, that will soon change. Both sewer pump stations will undergo significant renovations at a cost of approximately $47 million. Improvements will include new pumping equipment; new discharge piping and valves; upgraded wet-well access; and new controls and instrumentation.

Triton Construction of St. Albans was awarded the contracts for the pump station improvements through a public bidding process. The work is expected to be completed in 2028.

Backflow Prevention Project

In Spring 2026, Huntington Water Quality Board members approved accepting $7,358,000 in grant funding for a project that will aim to lessen nuisance street flooding and basement backups in residences.

This project will include the installation of valves in combined storm and sanitary sewer overflow (CSO) outfalls that can withstand water pressure from the Ohio and Guyandotte rivers during high-water events. This will keep river water from inundating our sanitary sewer system.

This project will make the collection system more efficient by mitigating some street flooding and basement backups; reducing the number of CSO events that occur upstream in our sewer system by allowing additional storm water storage in our system, which was previously taken up by river water; and by reducing the amount of river water that is pumped and treated at the Huntington Wastewater Treatment Plant.

When Huntington’s combined sanitary sewer and stormwater collection system was originally built in the early 1900s, it included 22 CSO outfalls. These were large pipes that funneled sewage and stormwater directly into the Ohio or Guyandotte rivers.

By the 1960s, the federal government became more focused on improving water quality and implemented numerous regulations for states, counties and cities. As a result, Huntington built its existing wastewater treatment plant in 1964 in Westmoreland.

Around the same time, the Greenup Locks and Dam was constructed. The Locks and Dam raised the normal pool of the Ohio River by 10 feet in the Huntington area. This submerged many of the outfalls along the river and made it easier for Huntington’s collection system to become inundated with river water.

The 22 CSO outfalls remain today, relics of the city’s old collection system. When river water backs up into these outfalls, it causes nuisance street flooding in some areas and basement backups in homes, as well as takes up space to allow storage of localized sanitary and storm water flow that can be pumped and treated at the wastewater treatment plant.

The project could be completed sometime in 2028.

Route 10 Extension Project

The Route 10 sanitary sewer extension project will extend service to Hite-Saunders Elementary School and to approximately 345 residential and commercial customers in the vicinity of Route 10, Green Valley Road and Norwood Road.

The West Virginia Department of Environmental Protection approached the Sanitary Board about this project a few years ago because of concerns about several business’ and homes’ failing sewer systems along Route 10 and the pollution risk it posed to nearby creeks and streams.

Funding for this project comes from the West Virginia Water Development Authority, West Virginia Department of Environmental Protection, West Virginia Infrastructure and Jobs Development Council, an American Rescue Plan Act (ARPA) grant from the Cabell County Commission, the Cabell County Board of Education, a low-interest loan and from customers who will be served by the extension project. 

Work began in March 2025 and is expected to be completed in 2027.

Fourpole Creek Sanitary Pump Station

In Spring 2026, U.S. Senator Shelley Moore Capito for her efforts in securing a $10 million Congressionally Directed Spending allocation for the rehabilitation of the Fourpole Creek sanitary pump station.

This funding will allow for the replacement of the pumps and controls in this station, which is a critical piece of infrastructure in our collection system. Approximately 85 percent of the sanitary flow in Huntington passes through this sanitary pump station in its path to the wastewater treatment plant in Westmoreland.

Construction on this rehabilitation project could begin sometime in 2027.